More work ‘still required’ for Ottawa’s LRT east extension

News Room
By News Room 4 Min Read

OC Transpo is getting closer to its next phase before opening the LRT Line 1 east extension to Orléans, but says some additional work is required to increase the system stability.

According to a Nov. 18 memo from general manager Rick Leary, software upgrades were completed on Sunday, Nov. 15. The line was shut down during the morning to allow sub-contractor Hitachi to complete the reprogramming of the train-control software.

Leary said the transit authority ran the system “to ensure the successful upgrade and are now ready to proceed with additional system testing.”

The next phase is expected to commence Nov. 22 with “ full-line testing ” and trains operating between Tunney’s Pasture and Trim stations for the first time, although passengers still won’t be able to ride any further east than Blair Station.

“This next stage will be the first time that (Rideau Transit Maintenance) launches 23 trains running from Tunney’s Pasture to Trim stations, operating approximately every four and a half minutes during peak periods,” Leary said in a memo to councillors. “Exercising the full line allows OC Transpo and RTM to test vehicles, schedules, staffing assignments and the reliability of all systems under normal operating conditions before progressing to pre-trial running.”

The east extension to Orléans has been long-delayed by various complications since engineers discovered a “spalling” issue in January that forced dozens of O-Train Line 1 trains offline for repairs.

Leary said RTM was regularly providing the required number of trains. Yard operations continue to improve, ensuring that trains are deployed on time.

At a transit committee meeting in September, Leary said the extension was “progressing as planned” and that the pre-trial testing phase was forecast for early October. That date was then set back to mid-November to accommodate the software upgrades.

In a memo this week, Leary said officials found that “upgrades were needed to equipment that supports communication between trains and the control system in the Transit Operations Control Centre.”

Those upgrades were completed last week and required the suspension of train testing “for a few days,” Leary said.

He said the upgrades would improve the reliability of the system.

Leary also said “additional work is still required to increase the reliability” of the LRT’s traction power substation. OC Transpo will monitor the reliability of the system to ensure it is ready for pre-trial running, he said.

The pre-trial running phase is expected to last about one week, officials have said, followed by the trial running phase when all train systems must meet performance, safety and reliability standards for 21 consecutive days.

Once the 21-day trial running is considered complete, there will be a series of certifications, approvals and regulatory documents that will take five to 10 days before the trains will be ready for passengers on the east extension.

Take control of your search results. Make the Ottawa Citizen a preferred source on Google and see verified local reporting first.

Related

Share This Article
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *