Last year, Ottawa’s power utility asked for an electricity bill increase that customers called “outrageous,” “inhumane” and “a slap in the face.”
Hydro Ottawa wanted to raise its electricity distribution rates by more than 50 per cent over five years — a spike that would see residents paying hundreds of dollars more to keep their lights on.
The utility said the steep increase in rates was necessary to meet steep challenges.
Facing growing power demand, Hydro Ottawa told the Ontario Energy Board (OEB) — the provincial regulator that sets the rates utilities can charge — it needed to spend $1.2 billion on new and upgraded energy infrastructure, a capital investment plan “of unprecedented scope and scale.”
The initial application to raise rates did not pin the blame on data centres. But in a presentation to Ottawa city council this summer, Hydro Ottawa CEO Bryce Conrad singled them out for adding to the utility’s growing burden.
“It’s no secret that there’s a lot of tension these days around data centres, AI technologies, and their tremendous appetite for power,” Conrad told councillors.
Hydro Ottawa, he said, was already facing a historic volume of connection requests from large energy users like hospitals and research labs. Now it was experiencing a surge in requests from data centres as well.
He warned that by the end of this year, new requests to connect to the grid could exceed the total amount of power used by the entire city of Ottawa.
As of June, data centres — Conrad didn’t say how many — were responsible for more than half of the potential demand.
A Star examination of over 20,000 OEB regulatory filings found that in cities and towns across Ontario, utilities are facing critical power capacity challenges driven or exacerbated by the data centre boom.
Governments are scrambling to respond to data centres and their enormous energy needs. Meanwhile experts and advocates worry that regular people will end up subsidizing the energy infrastructure build out that’s needed to support these facilities.
Lawrie Gluck, an independent consultant representing the Consumers Council of Canada in regulatory proceedings with the OEB, warns that without a comprehensive policy response that ensures all costs are recovered from data centres, consumers will end up paying some of the bill.
“This will cause very significant rate increases for all other customers in Ontario.”
To meet the rise in power demand, Hydro Ottawa said it needed to spend millions of dollars on new transformer stations — local nodes in the power network that deliver electricity to homes, businesses, schools, hospitals and beyond.
The utility blamed the increase in demand on several drivers — including population growth, an increase in electrification, and new large users, including a few potential data centres — and warned that some stations were already seriously overtaxed.
“Rapid growth in Kanata North, particularly in the technology sector, has strained existing (power) stations, pushing them to their operational limits,” the filings from Hydro Ottawa read.
“There has been a surge in large load requests in this region and data centre connection inquiries.”
Typically, rate hike applications with the OEB attract scant attention. But Hydro Ottawa’s submission, which would see a typical residential customer paying $73 more for electricity distribution in 2026 and $224 more by 2030, struck a nerve.
Blake Hamilton, a 45-year-old administrative co-ordinator, was one of nearly 150 customers who wrote letters to the board.
“I’ve seen it in my budget,” Hamilton told the Star. “Groceries, other bills, utilities … everything is going up.”
Hamilton said he was worried about a “cumulative erosion of affordability” — a common theme in the letters. One single mother wrote that the rate increase, on top of fuel and food costs, could make the difference in her ability to both pay her bills and “feed myself and my children.”
Hydro Ottawa’s own data supports the claim that a rising share of its customers are struggling: Roughly one in six residential customer accounts were in arrears at the end of 2025, according to utility data, a share that has more than doubled since before the pandemic.
“Hydro Ottawa remains committed to delivering safe, reliable electricity while keeping service accessible and supporting our customers through broader economic pressures,” spokesperson Susan Fekete said.
The OEB was not convinced: it slashed Hydro Ottawa’s spending plan. Following outrage from customers and submissions from advocacy groups, the board accepted a $214 million cut to the utility’s capital spending and later removed $11 million from its operational budget, citing affordability.
The changes lowered residential customers’ bill increases to $5.30 a month this year, from the $6.08 Hydro Ottawa had asked for.
“Energy is a critical service to Ontario’s people, farms and businesses. The need for that service is growing at a nearly unprecedented rate,” said an OEB spokesperson.
“However, the growth of our energy system cannot mean those people, farms and businesses are required to pay unconstrained costs. Our decision on Hydro Ottawa’s rates and the process followed to get to that decision reflect the OEB’s mandate to balance affordability for people and businesses with support for energy system investments.”
The OEB permitted Hydro Ottawa to nearly double its spending on capital items, such as poles and wires, in the next five years, the spokesperson noted, adding that Hydro Ottawa and interveners came to an agreement on many of the key issues in the case, including the capital spending cut.
But at a June Ottawa city council meeting, the Hydro Ottawa CEO took aim at the OEB, calling its regulatory process “brutal.”
“I appreciate the need to keep rates low, but when you’re on the cusp of or in the midst of exponential growth in demand, they need to change their mindset,” he said.
In his presentation, Conrad opened the utility’s books, showing councillors rising cost pressures alongside a massive potential power demand from data centres.
“We are being asked to build and support in the next two to three years what has taken us the better part of 110 years to build,” he said.
Fekete, Hydro Ottawa’s spokesperson, said the OEB’s rate decision doesn’t change the utility’s obligation to evaluate and process connection inquiries.
But Conrad’s public blast pointed to a gap: if data centres are driving up energy infrastructure costs, and regular people aren’t going to bear those costs, who will?
As AI has taken off, governments have scrambled to respond to the resulting data centre boom.
Historically, Ontario’s electrical system operated on a first come, first served basis: if a new large user asked to connect, and the grid had sufficient capacity, utilities were required to connect the new customer.
Hydro Ottawa told the Star that new large users typically pay for their “connection assets” — like the poles and wires required to connect to a local transformer station — but that “broader system investments” are recovered through the process at the OEB.
Late last year, the Ford government passed new legislation that would change those rules and force data centres to meet certain requirements to connect to the grid.
But those requirements remain undetermined. In August, the province released a data centre “playbook” that set a series of principles — including that data centres should pay for their own electricity costs — but does not yet spell out legally-binding regulations.
The province is “moving forward with tough new measures,” including rolling out a new rate class that will see both new and existing data centres pay higher rates, Noah Mawji, a spokesperson for Energy Minister Stephen Lecce, recently told the Star.
“Every project must deliver meaningful benefits to local communities, and Ontario’s Data Centre Playbook lays out our plan to protect ratepayers, attract new investment, and keep Canadian data sovereign and secure in Canada.”
Gluck, the independent consultant, says he believes the government may need to go beyond creating a new rate class and introduce contractual obligations that hold data centres responsible for their expenses, even if they were to shut down before costs are fully recovered.
“The government has made statements that data centres will pay the full cost of electricity to avoid cross-subsidies from other customers. However, based on the limited information currently available, it remains unclear what this really means.”
Power Struggle: In cities across Ontario, utilities are facing urgent power capacity challenges driven by data centres. In this four-part series, Star journalists look at how local residents are footing the bill — despite government assurances that data centres should not shift their costs onto the rest of us.