Last year, two power companies responsible for keeping the lights on in Cambridge, Ont., received a letter that repeated the same word nine times.
“Urgent,” it began in boldface type.
The letter came from the Independent Electricity System Operator (IESO), whose job it is to ensure the grid has enough power to meet the province’s needs.
In Cambridge and the surrounding region, the grid operator identified a pressing problem. “Urgent” growth in electricity demand had created “urgent” needs, it said, and required “urgent” investments to increase power capacity to the area.
“Proceed immediately” with projects to address the shortfall, the IESO letter said to GrandBridge Energy, the local utility, and Hydro One, which operates a network of transmission lines in the province.
That same fall, at a drab industrial park in northwest Cambridge, another business was in the midst of its own project. This one involved a different kind of infrastructure: some of the world’s most powerful computing hardware, the kind used to train and run frontier artificial intelligence models.
The urgent letter does not blame any particular power user for the sudden increase in demand for electricity. But in a short list of reasons for the load growth in Cambridge, the letter cites one first: “large new data centre customers.”
Data centres are proliferating rapidly. The one in Cambridge stands apart thanks to its anchor tenant: Cohere, a Toronto AI startup that Prime Minister Mark Carney’s government has drawn into the nexus of Canada’s strategic interests.
The federal government pledged $240 million for Cohere to access computing power at this data centre and announced a direct $1.6 billion equity investment in Cohere last month, buying every Canadian a stake in its future.
Carney says Canada needs to build its own data centres to protect its sovereignty and control our AI destiny. But the data centre boom has also provoked a fierce backlash, and critics see them as a manifestation of Big Tech’s tendency to put profits before people and extract private value from public goods.
Provincial authorities, local utilities and facility operators, citing confidentiality concerns, have withheld information about where data centres are being built, who owns, operates, and uses them, and how much power they will draw from the existing power grid.
To help fill this vacuum, the Star used artificial intelligence to search more than 20,000 regulatory filings at the Ontario Energy Board, whose mandate includes setting the rates that utilities can charge consumers. In cities and towns across Ontario, reporters found, utilities are already facing critical power capacity challenges driven or exacerbated by the data centre boom.
Nowhere is the tension between Canada’s AI ambitions and its local costs more obvious than in Cambridge, where the needs of Cohere, Ottawa’s tech darling, helped set off a rapid and expensive scramble for solutions.
Local residents and businesses are already footing higher bills for a sudden surge in power demand — despite assurances from the federal and provincial governments that data centres would not shift energy costs onto ratepayers.
Kyle Lastovica, a spokesperson for Cohere, told the Star the company supports the government principle that data centres should pay their own way.
Data centres “should create lasting economic benefits, pay for their own energy rather than shifting electricity costs onto Canadians, minimize environmental impacts, and operate with transparency,” Lastovica said.
Lastovica added that Cohere does not own or operate the data centre in Cambridge. But Cohere is a tenant there, the Star has confirmed.
(The parent company of the Toronto Star, along with a coalition of other media organizations including the Guardian, the Atlantic and Condé Nast, is suing Cohere for copyright infringement.)
Cambridge’s saga raises “layers upon layers upon layers of questions,” said Mark Winfield, a professor of environmental and urban change at York University — questions about sustainability, sovereignty, and spending to support the infrastructure necessary for data centres.
“The main one,” he says, “is who pays — and is that fair?”
In an application GrandBridge brought to the Ontario Energy Board (OEB) last year, the utility described a plan to bring more power online quickly.
It would not be cheap.
The IESO’s letter recommended that GrandBridge immediately start work on a new transformer station, at a cost of $40 million. Such stations are a local node in the power network: they distribute power to homes, businesses, schools, hospitals and beyond.
The letter also told Hydro One to immediately begin upgrading circuits and constructing other transmission infrastructure that feeds the region, at a cost of up to $390 million. The upgrades would remove a limitation that restricts power capacity at Cambridge’s three existing transformer stations.
“Without immediate action,” GrandBridge warned in its application, the shortfall in Cambridge could create “unacceptable” outcomes. That included difficulty managing outages, which raised the possibility of extended blackouts.
Ali Hooshyar, an energy systems expert at the University of Toronto, said the language surrounding the new transformer station is unusual.
“Usually, things do not happen so urgently,” Hooshyar said. “A new transformer is not something that you go and buy off the shelf from Walmart.”
Even with immediate action, the new transformer station would not be ready until 2028 — and that caused another problem for GrandBridge. Forecasts showed Cambridge’s transformer stations nearing their capacity limits this year, and in some scenarios exceeding those limits by the summer of 2027.
So GrandBridge applied to the OEB for permission to launch a program to help bridge the gap. “Gridshare,” as the program was called, would pay businesses and institutions to reduce demand at peak periods. The utility budgeted around $3 million for the program over three years.
Board staff probed the utility on why this capacity gap existed in the first place: What caused the acceleration in demand? And why didn’t the utility move to build the new transformer station sooner?
GrandBridge told the board it had known for several years that it would eventually need a new transformer station in Cambridge. It acquired land for the future station in 2018.
But electricity demand was growing at a gentle pace, according to GrandBridge. There was no justification to start building the new station: capacity was sufficient to meet that demand.
Suddenly, that changed.
Planning for the new station “as an urgent need” began in late 2024, “after a significant growth in new load arose,” GrandBridge wrote.
Demand across the three stations serving Cambridge was forecast to jump by more than 20 megawatts (MW) in 2025, and more than 65 MW in 2026, data filed by the utility shows.
This is an enormous surge for a small city like Cambridge. It represents an increase of more than a quarter of the Cambridge stations’ previous power load, compared to roughly 2 per cent growth in the years prior.
At the board, GrandBridge blamed the rise on a list of drivers: “New data centres, commercial developments along major highways, urban densification, residential growth, and transportation electrification.”
The utility would not say how many data centre customers it has, or identify their power demands. But the utility did answer a question about how many new large customers it has connected in recent years.
Only one, GrandBridge said: a customer that connected in 2025.
The Star sent a detailed list of questions to GrandBridge Energy for this story.
In response, the utility replied with a statement attributed to Umar Waqas, GrandBridge Energy’s vice president of grid modernization. It did not address the Star’s questions about how much of the rapid demand increase came from data centres, how many data centres were involved, or the role of the Cohere data centre in northwest Cambridge, which previously housed a smaller data centre and underwent a major expansion last year.
“Protecting our customers’ privacy and confidential business information is an important part of our responsibility as a local electricity distribution company,” Waqas said, citing privacy laws and OEB requirements.
Waqas did say, however, that data centres currently represent around 12 per cent of the total demand in Cambridge, up from approximately 1 per cent in years prior.
Other public documents provide details about the identity of the large customer that joined the grid in 2025.
One of the IESO’s responsibilities is to conduct “system impact assessments,” which examine whether new connections to the grid could affect the reliability of Ontario’s power system. Its reports are posted publicly.
GrandBridge applied to the IESO to connect a huge 80 MW data centre to its Cambridge transformer stations. That customer planned to join the grid in 2025, adding 16 MW of load that year and reaching its full load this year. Running at full capacity, the data centre would use as much electricity as approximately 20,000 homes.
The IESO gave conditional approval, finding no significant reliability issues that would prevent connection to the grid.
The document does not identify the data centre or say where it is. But Cambridge planning staff told the Star that the city has only one large data centre in operation, the one in the northwest corner of the city — where Cohere is the anchor tenant.
City staff approved the major expansion, which involved at least four U.S. companies: Coreweave, a company that rents AI computing infrastructure and partnered with Cohere, as well as Related Digital, Ascent, and TowerBrook Capital Partners, who are described as joint developers. The data centre also houses at least one other tenant that predates the expansion.
Multiple experts said all available evidence points to the data centre as the primary culprit for Cambridge’s urgent capacity problems.
Winfield, who has worked in energy policy for decades, said that residential and commercial growth are “highly unlikely” to cause such a large and sudden increase in demand.
“They don’t give giant surges. They’re a curve that goes gently upwards.”
Across the continent, he added, almost all electricity growth is coming from data centres.
“It’s pretty clear the driver is the data centre,” said Winfield. “I think that’s the bottom line.”
The cost of addressing the power shortfall in Cambridge will end up on every resident’s electricity bill.
Customers in Cambridge, as well as in neighbouring North Dumfries and the County of Brant, began receiving an extra charge to pay for the Gridshare program on their energy bills after the OEB approved Gridshare in May. Those charges are slated to continue for two more years.
For a typical residential customer, the charge — called a rate rider — amounts to less than a dollar a month. But the program as a whole will raise roughly $2 million to pay participants to cut demand when the city needs capacity most.
GrandBridge fought at the OEB to keep the identities of the program’s participants confidential. But one local business voiced its enthusiasm in a GrandBridge grant application: the data centre.
In a letter of support, a senior manager described the data centre as a “potential participant” that is “eager to explore the benefits” of such a program — raising the possibility that Cambridge residents could wind up paying the data centre to reduce its own demand.
Environmental permits point to how the data centre could participate: by drawing on the more than 50 MW produced by diesel generators the province has approved for use at the property, swapping cleaner electricity from Ontario’s grid for polluting fossil-fuel-powered generation on-site.
A spokesperson for Related Digital, the company that manages operations at the site, said the data centre did not ultimately participate in Gridshare this summer, but did not rule out joining in future years.
“We do not currently have the ability to join as our generators are only permitted for emergency power and testing,” she said.
The OEB said that the decision to approve Gridshare “was made by an independent Commissioner based on the evidence on the record.”
If the OEB approves it, the cost of building Cambridge’s new transformer station will result in further increases to power bills in Cambridge.
GrandBridge plans to ask the board next year to approve a second rate rider to recover its investment of approximately $40 million for the station. Waqas, the utility’s vice president, reiterated in response to further questions that planning for the station had been underway since 2018, and it will support residential, commercial, and industrial growth.
That rate increase needn’t have appeared on customers’ bills so soon, however. Initially, the IESO approved GrandBridge’s 80 MW data centre application only if it agreed to install equipment that rejects power load if the system is overtaxed.
GrandBridge asked the IESO for an alternative: instead, it would move the construction of the new transformer station ahead by two years, from 2030 to 2028. The IESO approved the data centre’s connection with the requirement that the new station “be built in a timely manner.”
Waqas said the new station is part of a long-term plan to meet Cambridge’s growing electricity needs, and that “accelerating the timing of a planned investment is different from being the sole reason for that investment.”
“Public filings alone do not establish that residents are paying the costs attributable to an individual customer’s connection,” Waqas said, adding that outside experts do not have access to full planning information or customers’ financial arrangements.
The IESO also noted that the majority of electricity growth in the wider region, which also includes Kitchener, Waterloo, and Guelph, is from sources other than data centres.
Winfield said the key question GrandBridge is “obfuscating” is how much of Cambridge’s increase in demand comes from normal growth versus one very large user.
Cambridge residents are “being asked to pay the costs of providing the infrastructure for this very large new load,” Winfield said.
“It seems to be pretty fundamentally unfair,” he said.
The Star’s reporting shows Cambridge is not alone. In other cities and towns in Ontario, utilities are struggling to absorb the cost of new infrastructure as the data centre boom expands.
Both the provincial and federal governments have released frameworks that state, in principle, that Canadians should not bear the costs of data centres’ power needs.
But “that’s exactly what seems to be happening,” said Winfield.
Ontario released a data centre “playbook” in August, which includes as a core principle that these facilities “must pay for their full electricity costs.”
The province is “moving forward with tough new measures” to do that, Noah Mawji, a spokesperson for Energy Minister Stephen Lecce, said — including rolling out a new rate class that will see both new and existing data centres pay higher rates.
“Every project must deliver meaningful benefits to local communities, and Ontario’s Data Centre Playbook lays out our plan to protect ratepayers, attract new investment, and keep Canadian data sovereign and secure in Canada.”
The federal government’s “responsible data centre development principles,” announced in September, include “clear expectations” that “data centres must not shift electricity costs to Canadians.” Cohere has signed onto those principles, as have Anthropic, OpenAI, Google, Meta and NVIDIA.
“Data centres should bear the electricity infrastructure costs attributable to their projects, not pass them on to households and local businesses,” a spokesperson for AI Minister Evan Solomon’s office said. “Federal support for Cohere does not change that.”
Regulations may eventually better protect Canadian consumers, but data centres have also become an avatar for broader concerns about AI and the tech giants who create it, Winfield said.
“We have large portions of Canadian society who are expressing profound concerns about where AI is taking us in terms of society, social relations, employment, privacy — you know, everything,” Winfield said.
Debate at the community level, where proposals for data centre moratoriums have drawn huge public engagement, continues to veer into this broader tangle of questions.
“How much do we want to facilitate that expansion of AI?” Winfield asks. “Or is this a leverage point that society can use to slow this down a bit and exercise some degree of control, which governments otherwise seem to be failing to do?”
Power Struggle: In cities across Ontario, utilities are facing urgent power capacity challenges driven by data centres. In this four-part series, Star journalists look at how local residents are footing the bill — despite government assurances that data centres should not shift their costs onto the rest of us.